Implementation of the Earliest Due Date Method in Sample Production Scheduling of Cushion Products at PT XYZ
DOI:
https://doi.org/10.33506/mt.v12i1.5289Keywords:
Cushion Production, Earliest Due Date (EDD), Production Efficiency, Production Scheduling, Visual Basic for Applications (VBA)Abstract
PT XYZ faces delays in completing sample production of cushion products due to high sample demand and the absence of a systematic production scheduling method. This condition results in suboptimal job prioritization and delays in sample completion. Initial observations indicate that sample production delays reached up to 6 days. This study aims to implement the Earliest Due Date (EDD) method in sample production scheduling to minimize delays and improve production efficiency. The EDD method is used to determine job priority sequences based on due dates by utilizing processing time data from each production department. The implementation of the EDD method is integrated into a scheduling system based on Visual Basic for Applications (VBA) to facilitate data processing and production schedule control. The results show that the application of the EDD method is able to reduce sample completion delays from 6 days to a maximum of 4 days and decrease the level of sample production delays by 33.3%. Therefore, the EDD method is proven to be effective in improving the efficiency and accuracy of cushion sample production scheduling.
References
Agi, R., Putra, S., Lestanti, S., & Febrinita, F. (2024). Optimasi aturan prioritas untuk keefektifan penjadwalan mesin bordir di rumah produksi delvia. JATI (Jurnal Mahasiswa Teknik Informatika), 8(5), 9898–9906.
Agustin, J., & Nurjanah, N. (2024). Pengukuran Waktu Baku Aktivitas Labelling Di Perusahaan Third Party Logistic (3PL) PT X Menggunakan Metode Stopwatch Time Study. Jurnal Logistik Bisnis, 14(2), 27–32.
Azzat, N. N., & Zulfa, M. C. (2023). Optimasi Penjadwalan Produksi Dengan Algoritma Heuristik Pour Untuk Reduksi Makespan Pada CV CJ Furniture Optimization of Production Scheduling Using Pour Heuristic Algorithm for Makespan Reduction in CV CJ Furniture. Jurnal Ilmiah Teknik Industri, 14–22.
Rianti, T., Kurnia, Y., & Hilman, M. (2024). Menentukan Waktu Baku Untuk Meningkatkan Produktivitas Kerja Dalam Proses Produksi Lemari Menggunakan Metode Time Study Pada Ikm Ihsan Alumunium Di Padaherang. Intriga (Info Teknik Industri Galuh), Jurnal Mahasiswa Teknik Industri, 2(1), 61–70. https://doi.org/10.25157/intriga.v2i1.4472
Kurniawan, N., & Suseno, S. (2023). Optimasi Sistem Penjadwalan Produksi Dengan Metode Nawaz Enscore Ham (NEH) Pada PT Sinar Semesta. Jurnal Inovasi dan Kreativitas, 3(1), 24–33. https://doi.org/10.30656/jika.v3i1.6001
Mustajab. (2023). Effective Production Planning and Scheduling: Literature Review. Vifada Management and Social Sciences, 1(2), 54–72.
Qu, L., Zhang, J., Wang, D., Zhang, L., & Wu, Z. (2024). Study on Fatigue Allowance Formulation Based on Physiological Measurements. Sensors, 24(22), 2024. https://doi.org/10.3390/s24227393
Rahmadan, M., & Gunawan, C. E. (2024). Perancangan data flow diagram aplikasi tabungan sampah PT Pusri Palembang. Prosiding Seminar Nasional Mini Riset Mahasiswa, 3(1), 1–9.
Rahmah, G. M., Fauziah, K., & Suroso, F. (2024). Implementasi Metode Earliest Due Date ( EDD ) untuk Penjadwalan Produksi. Journal of Manufacturing and Enterprise Information System, 2(1), 65–72. https://doi.org/10.52330/jmeis.v2i1.267
Setyowati, L., & Lasiyono, U. (2024). Optimalisasi Perencanaan dan Penjadwalan Produksi : Kunci Meningkatkan Efisiensi Operasional. Jurnal Inovasi Manajemen, Kewirausahaan, Bisnis dan Digital, 1(4), 50–56.
Tambunan, B. H., & Simanjuntak, J. F. (2022). Analisis Pelaksanaan Kas Kecil (Petty Cash) Pada PT Deli Jaya Samudera. Journal of Economics and Business, 03(01), 41–48.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Rikan Sholikul Musa, Noor Nailie Azzat, Gunawa Muhammad, Dwi Retna Sulistyawati, Boedi Lofian

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.